Home / Ministry  / 14 States/UTs have been 100% electrified by Indian Railways

14 States/UTs have been 100% electrified by Indian Railways

37011 RKM of Broad Gauge network of IR electrified in past nine years As on 30.06.2023, 59,096 Route kilometers (RKM) of Broad Gauge network of Indian Railways (IR) have been electrified. Out of which, 37,011 RKM

  • 37011 RKM of Broad Gauge network of IR electrified in past nine years

As on 30.06.2023, 59,096 Route kilometers (RKM) of Broad Gauge network of Indian Railways (IR) have been electrified. Out of which, 37,011 RKM have been electrified during the past nine years only. State/UT wise details of electrification are as under:

SNSTATE/UTElectrified BG RKM as on 30.06.2023
1Chandigarh16
2Chhattisgarh1,199
3Delhi183
4Haryana1,701
5Himachal Pradesh67
6J&K298
7Jharkhand2,558
8Madhya Pradesh4,822
9Meghalaya9
10Odisha2,822
11Puducherry21
12Telangana1,858
13Uttar Pradesh8,482
14Uttarakhand347
15Bihar3,614
16Andhra Pradesh3,841
17Tamil Nadu3,659
18Maharashtra5,441
19West Bengal3,682
20Kerala947
21Gujarat3,435
22Punjab1,915
23Rajasthan4,387
24Goa147
25Karnataka2,844
26Assam801
27Arunachal Pradesh
28Manipur
29Mizoram
30Nagaland
31Tripura
 Total59,096

Sometimes, there is some delay in getting statutory clearances required for execution of electrification works.

For timely completion of railway electrification work, various steps have been taken by Indian Railways which include among others; formation of Project Monitoring Group (PMG) portal to resolve the constraint being faced during commissioning, creation of ‘Gati Shakti Directorate’ in Railway Board for smooth & speedy approval of projects at Railway Board level and ensuring effective project monitoring mechanism. In addition, large size projects are being executed in ‘Engineering Procurement and Construction’ (EPC) contract mode, assured funding is being arranged and financial powers are decentralized to field units to expedite the project execution & completion.

Existing Broad Gauge network falling in the following State/Union Territory have been 100% electrified:

SNState/Union TerritorySNState/Union Territory
1Chandigarh8Madhya Pradesh
2Chhattisgarh9Meghalaya
3Delhi10Odisha
4Haryana11Puducherry
5Himachal Pradesh12Telangana
6J&K13Uttar Pradesh
7Jharkhand14Uttarakhand


Electrification of 3,614 Route kilometer (RKM) out of 3,710 RKM and 3,435 RKM out of 3,862 RKM have been completed in the State of Bihar and Gujarat respectively.

Indian Railways (IR) has aimed to become Net Zero Carbon Emitter by 2030. IR has taken a number of initiatives to reduce its carbon emissions which include use of energy efficient technologies like completely switching over to production of three phase electric locomotives with regenerative features, use of head on generation (HOG) technology, use of LED lights in buildings and coaches, star rated appliances, water conservation and its management and afforestation.

Further, the key strategies that have been identified for achieving the Net Zero Carbon emission target are procurement of power through renewable energy sources; shifting from diesel to electric traction; promotion of energy efficiency; and afforestation.

This information was given by the Minister of Railways, Communications and Electronic & Information Technology, Shri Ashwini Vaishnaw in a written reply to a question in Lok Sabha today.

—–

komal.hospi@gmail.com

Review overview
NO COMMENTS

Sorry, the comment form is closed at this time.